What are the measures to prevent the wall cracking of aerated concrete blocks?

Date of issue: 2019-11-04 Author: Click:

prevent Aerated concrete block What are the measures for wall cracking?

Before plastering the aerated concrete block wall, the floating soil and floating plaster on the block surface shall be cleaned up. The missing edges and corners and the mortar is not full shall be repaired with mixed mortar. The wall shall be watered the day before plastering. Before plastering, the mortar interface agent or 108 glue shall be sprayed (or brushed) once. After plastering, the interface agent or 108 glue shall be sprayed (or brushed) once again before there is no obvious crack on the surface.

1. Crack prevention between shear wall, concrete beam slab and masonry:

(1) For the infilled wall of the shear wall, when the wall is laid to the next layer (i.e. the beam bottom), the auxiliary solid small blocks (or solid standard bricks) shall be laid obliquely to make the masonry closely contact the beam bottom. Masonry mortar shall be full.

(2) If the shear wall protrudes from the wall surface, the wall surface shall be plastered first, and then the concrete surface shall be plastered after the wall plastering layer is dry, and the plastering layer of the concrete surface shall be pressed on the wall plastering layer, so that the shrinkage crack at the connection is covered by the plastering layer plastered after the concrete surface.

(3) If the shear wall or beam column is flush with the block wall, a layer of 2-3mm thick 1:3 cement mortar shall be plastered on both sides of the joint before plastering, and then a layer of glass fiber cloth (100mm wide for concrete and wall respectively) shall be pasted with plain mortar (cement: 108 glue: water=1:0.5-0.8:6-8), and then plastered.

 


 Autoclaved aerated concrete blocks


2. External wall crack prevention

Because the structure is constructed with large formwork, the concrete surface is relatively smooth. Before painting, concrete interface agent is used to enhance the bonding effect between the painting layer and the base layer.

When the exterior wall surface course is painted, the mortar can be mixed with appropriate amount of Danqiang fiber to enhance the crack resistance of the exterior wall.

Danqiang silk fiber is used in externally painted mortar to improve its anti cracking performance, impact load resistance, flexibility resistance, and effectively control and reduce the generation and expansion of cracks in mortar. Danqiang silk fiber also has the advantages of simple construction, corrosion resistance and alkali resistance, economy and reliable effect.

3. Finished product protection

(1) After the door frame is installed, iron sheet shall be nailed on both sides of the door with a height of 800mm to protect it during construction, and it is strictly prohibited to damage it by carts.

(2) The equipment slot hole shall be reserved. If it is not reserved or missed, the cutting machine shall be used for slotting. Hard chiseling is strictly prohibited to damage the wall. If it is loose, it will be reinforced.

(3) The floor mortar shall be removed in time to avoid bonding with the ground and affecting the construction of the next process.

(4) During the shipping process, the blocks shall be loaded and placed with care, the amount of each room shall be calculated, and the blocks shall be stacked neatly.

(5) Do not damage the built wall and the corners of doors and windows when erecting and removing scaffold.

The content of this article comes from the Internet. If you have any questions, please contact us!

Website: //gznt120.cn/news/456.html

key word: Shenyang aerated concrete block , Manufacturer of aerated concrete block , Wholesaler of aerated concrete block

Recent browsing:

contact information

Liaoning Hongsheng Technology Co., Ltd. (formerly Liaoning Qinzhen Environmental Protection Building Materials Co., Ltd.)

Company hotline: 13709811835

Website: gznt120.cn

Address: Gate 2, Building 7, Celebrity Mansion, No. 2-1, Jinyang Street, Hunnan District, Shenyang